A Meta-Model based-Simulation Optimization approach for controlling rework delay duration in construction: An Intelligent Metamodeling Approach
Articles in Press, Accepted Manuscript, Available Online from 25 October 2026
https://doi.org/10.22116/jiems.2026.588428.1639
Mohammadreza Davoodabadi Farahani, Alireza Habibi, Hossein Amoozad Khalili, Mohammad Ehsanifar
Abstract Background and Objective: Rework is one of the main contributors to cost overruns, delays, and reduced productivity in construction projects. Since this phenomenon has a nonlinear and stochastic nature, conventional analytical methods do not provide sufficient capability for modeling and controlling it. The objective of this study is to propose an integrated metamodel-based simulation–optimization framework to control the duration of rework-induced delays in construction projects.
Research Method: This study employs a hybrid approach combining mathematical modeling, discrete-event simulation, design of experiments (DOE), central composite design (CCD), regression-based metamodeling, and heuristic optimization. The Modified NBI method is also used to address the multi-objective optimization problem. The research data were collected from a five-story building project in Tehran as well as 55 construction projects in the Middle East during 2015–2020. The results indicate that factors such as rework frequency and duration, workforce experience, conflicts among project stakeholders, payment delays, and political conditions are among the most influential contributors to rework. Moreover, the proposed metamodel transforms the simulation objective function from a black-box representation into a more explicit and solvable form, thereby reducing the computational burden of the optimization process.The findings suggest that integrating simulation, metamodeling, and optimization can provide an effective approach for controlling and reducing rework-related delays in construction projects. This framework improves decision-making accuracy while enabling the identification of optimal and Pareto solutions at a lower computational cost.
Simulation based optimization of multi-product supply chain under a JIT system
Volume 7, Issue 1, June 2020, Pages 87-106
https://doi.org/10.22116/jiems.2020.110009
Arman Sajedinejad, Erfan Hassannayebi, Mohammad Saviz Asadi Lari
Abstract It is scientifically challenging to determine the inventory level all through the supply chain in such a way that the desired objectives such as effectiveness and responsiveness of the supply chain system can be obtained. Simulation is a means for solving various problems which cannot be solved by regular exact models such as mathematical ones due to their complexity. The present paper is aimed at simulating lean multi-product supply chain system as well as optimization of the objectives of supply chain. Variables of the simulation model include two types of Kanbans namely withdrawal, and production to determine the inventory level, and batch size of delivery parts for each stage of supply chain. So, in this paper simulation model was developed for supply chains, taking into consideration the different production scenarios and were modeled and compared. A production scenario is adopted for each level of the chain in order to achieve the objectives. The use of meta-heuristic techniques leads us to optimization of these variables which helps decrease delay of both product delivery and inventory level of supply chain. In this case, Genetic Algorithm has applied to find the best variable values of each scenario (included in the right number of each Kanbans), aimed at decreasing the costs and delivery delays. An example based on a case study is given to illustrate the efficiency of the proposed approach. Considering each level of supply chain, the ratio between and among cost, inventory, and delivery delay variables were obtained.